Project: Design Modification of Sewage Collection and Treatment Plant

Assignment Name
Country
Design Modification of Sewage Collection and Treatment Plant
Nigeria
Location within Country
Professional staff provided by your firm
Lagos State
25
Name of Client Number of Staff
Chevron Nigeria Ltd
25
Address Number of staff months/Project Duration
Kilometre 19, Epe Expressway
PMB 12825, Lagos, Nigeria
300/12
Start Date Completion Date Approx. Value of services in Current US$
May, 1999
May, 2000
$34,438.00
Name of Associated Consultants If anyNumber of months of professional staff provided by associated consultants
  
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
  • Project Director/Coordinator: K.G. Till, P.Eng.,
  • John Rowe: Project Coordinator,
  • Mike Whiting: Project Coordinator
  • Project Team Leader: Engr. Oladapo Ogunbanjo
Narrative Description of Project
Project involved consulting engineering services for modification of the design of the Chevron Escravos Sewage Collection and Treatment Plant.
Description of actual services provided by your staff
The project involved modification of the sewage collection system and treatment plant to include a sludge digester and transfer of sludge digester to the centrifuge for dewatering, dewatered sludge collected in a bin within the STP building for onward transfer to sludge composting facility at Escravos; preparation of all construction documents consisting of drawings and specifications as well as comprehensive materials takeoff for sewage collection system and treatment plant.